Real bill, GDMTH, Norte Division, January 2026Period Dec 31, 2025 – Jan 31, 2026 · client data removed
Total for the period$8,276,293.65

Exact figures from the CFE bill, in MXN. The printed amount due, $8,276,294.12, includes $0.47 of prior balance.

Peak generation

kWh in the most expensive window (6–10 pm in winter, Norte division). On this bill, MXN 1.7081/kWh: 106% more than base.

What a BESS does to it

The BESS discharges here: the plant draws from the BESS, not from the grid. It is the main source of savings.

Drops · main source of savings

Fixed charge (supply)
Fixed monthly fee for having the service. It does not depend on your consumption. The BESS does not change it. No change
Base generation
kWh consumed in the cheapest window (overnight). On this bill, MXN 0.8279/kWh. Rises slightly: the BESS charges in this window, when energy costs least. Rises slightly
Intermediate generation
kWh in the intermediate window, most of the day. On this bill, MXN 1.4313/kWh. Practically unchanged. The system gives priority to moving consumption out of peak hours. No change
Peak generation
kWh in the most expensive window (6–10 pm in winter, Norte division). On this bill, MXN 1.7081/kWh: 106% more than base. The BESS discharges here: the plant draws from the BESS, not from the grid. It is the main source of savings. Drops · main source of savings
Capacity charge
Calculated on your billable demand (kW), dominated by your maximum peak demand. On this bill, 5,116 kW × MXN 401.78/kW: 29% of the bill before VAT. By shaving peak demand, billable demand drops and this charge with it. Drops
Distribution charge
Calculated on maximum measured demand, with a cap. On this bill, 5,419 kW × MXN 72.92/kW. Drops as the maximum demand the meter records goes down. Drops
Transmission
Charge for using the transmission grid, applied to all your kWh: MXN 0.1801/kWh on this bill. Practically unchanged: it is charged on total kWh, and the BESS shifts when you consume, not how much. No change
CENACE
Charge for operating the power system (CENACE, Mexico’s grid operator), applied to all your kWh: MXN 0.0076/kWh on this bill. Practically unchanged: it is charged on total kWh. No change
Ancillary services (SCnMEM)
Charge for ancillary services not included in the Wholesale Electricity Market, applied to all your kWh: MXN 0.0069/kWh on this bill. Practically unchanged: it is charged on total kWh. No change
Power factor
With less than 1 MW of contracted demand, CFE adds a surcharge below 90% and gives you a credit above it. With 1 MW or more, the threshold is 97%. At 95.73%, this bill carries a credit of MXN 14,297.98. Separately, since April 2026 the Grid Code has required 97% (0.97) from medium-voltage plants of 1 MW or more. The BESS inverter compensates reactive power continuously: a surcharge shrinks or turns into a credit, and an existing credit grows. Larger credit
VAT (16%)
Applied on the subtotal of all line items. Calculated the same way, on a smaller subtotal. All of ENEGRIN’s reconciliation includes VAT, like your bill. Drops with the subtotal
Public lighting fee (DAP)
A municipal levy that CFE collects on the bill. It is not an energy charge. The BESS does not change it. No change

To see the effect on your own bill, upload it to the Ollin Simulator

Guides

Grid Code

Grid Code: the 0.97 power factor required since April 2026

Since April 8, 2026, Mexico’s Grid Code (Energy Regulatory Commission resolution RES/550/2021) has required a power factor between 0.97 lagging and 1.0. It is measured every five minutes and must be met at least 95% of the time each month. It applies to medium-voltage plants with contracted demand of 1 MW or more, and to all high-voltage plants.

Regulation

Behind-the-meter batteries (BESS): what changed in 2026

The April 2026 rules issued by the CNE, Mexico’s energy regulator. Why a BESS at your plant does not require a storage permit if the energy is used only there. Which study CENACE (Mexico’s National Energy Control Center, the grid operator) requires and which technical standards the system must meet.